Installation guide example for making a Curb - Upstand for a 100x100 cm Skylight.

Requirements:

  • Wooden beams 69 mm wide
  • Carpentry tools (saw, hammer, nails/screws)
  • Roof covering material
  • Insulation material
  • PU Glazing tape
  • Wooden batten of 2"x1" (22x50 mm)
  • Silicone sealant Dowsil 791 Black Waterproof

Step-by-step plan:

1. Preparation of the Opening:

  • Measure and mark an opening of 1000x1000 mm on the roof.
  • Ensure the opening is accurate and cut it out.

2. Construction of the Curb - Upstand:

  • Use wooden beams 69 mm wide to build the Curb - Upstand.
  • The internal dimension of the Curb - Upstand must be 1010x1010 mm (10 mm larger in width and length than the opening).
  • Firmly assemble the Curb - Upstand.

3. Applying the Slope:

  • Ensure that one side of the Curb - Upstand is higher than the other side to create a slope of 5-6 degrees.
  • Use a rise of 10 cm per linear meter to achieve the correct slope. This ensures that rainwater can drain off.

4. Installation of the Curb - Upstand:

  • Place the timbered Curb - Upstand on the roof above the opening.
  • Securely attach the Curb - Upstand to the roof.

5. Insulating the Curb - Upstand:

  • Start applying roofing on the top of the Curb - Upstand.
  • Continue with the outer sides of the Curb - Upstand.
  • Continue with a piece of roofing over the old roofing.
  • Ensure the roofing overlaps the existing roofing by at least 15-20 cm.

6. Installation of the Skylight support (batten 22x50mm):

  • This is a crucial step, as this support will ultimately bear the weight of your Skylight.
  • Note: the warranty is void if no glazing tape is applied.
  • Use the recommended PU Glazing Tape, available on our website under the "Accessories" category.
  • The Skylight support consists of a wooden batten of 2"x1" (22x50 mm) and must be placed 47 mm below the top of the Curb - Upstand on all four inner sides (see technical drawing in product photos).

7. Applying glazing tape:

  • Apply glazing tape to the wooden batten to correct any unevenness and prevent pressure. This protects the lower laminated glass pane from cracking.

8. Installation of the Skylight:

  • After the Curb - Upstand is fully assembled and insulated, the Skylight can be installed.
  • Follow the installation instructions for correct placement.

Tips:

  • Always check if the Curb - Upstand is watertight before installing the Skylight.
  • Work carefully and ensure all measurements are accurate to avoid problems during installation.
  • Consult a professional installer for additional help and advice if necessary.